D
Dave
I really have two questions:
1) I have work center with 21 employees that are all interchangeable. I
need to book 5 of them to a task. It looks like if there is a conflict with
capacity, the system looks for the next available white space for 5 people.
The next day I have 4 people unused but because the units assigned was 5 it
skipped over that date.
2) I have a work center with 10 people 5 on first and 5 on 2nd shift. I
have a task that should take 32 hours to complete. There are many ways to
slice this like 1 person for 8 hours for 4 days. How do I fundamentally say,
I have this work requirement and please use up all available capacity. For
example, Monday I have already consumed 2 people for 8 hours which leaves 3
people for 8 or 24 hours. How do I get the system to use the 24 hours on
first and the remaining 8 hours needed on 2nd?
Thanks,
Dave
1) I have work center with 21 employees that are all interchangeable. I
need to book 5 of them to a task. It looks like if there is a conflict with
capacity, the system looks for the next available white space for 5 people.
The next day I have 4 people unused but because the units assigned was 5 it
skipped over that date.
2) I have a work center with 10 people 5 on first and 5 on 2nd shift. I
have a task that should take 32 hours to complete. There are many ways to
slice this like 1 person for 8 hours for 4 days. How do I fundamentally say,
I have this work requirement and please use up all available capacity. For
example, Monday I have already consumed 2 people for 8 hours which leaves 3
people for 8 or 24 hours. How do I get the system to use the 24 hours on
first and the remaining 8 hours needed on 2nd?
Thanks,
Dave