Hi,
Create a master project : open all the projects you want to manage, then:
Window / New Window / select all the plans you want, OK
Then activate the filter named "Milestone"
One way to achive this is to copy the milestones and use PASTE SPECIAL and
click the link option while pasting to a master file all the milestones. You
will have to manually copy and paste the milestones into a new master file,
but once done, your updates to individual files will reflect in the master
file.
Regards,
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.