Hi DannyG,
Is the specific times you want to reflect, related to the resoruce or the
task? Times are set up in various places. The first is the calendars where
you can change the time for each individual day or selected days, the second
is in the Calnedar tab of the 'tools/options', where the project defaut
setting is mad.
I suspect from yoru query that you want to change the default working day
from 8:00am to 5:00pm, to 9:00pm to 1:00am. This ensures that the
calculations required for project to give you a correct answer to your
schedule.
however you also need to select all the working days in the calendar used
for the project and manually change the start and finish times. However
remember that this shift works across two days. So the shift needs to show:
Start 12:00am finish 1:00am, then start 9:00pm finish 12:00am. This is the
reality on any particular day, you start the shift on one day and finish the
next hence the odd way of setting the time.
Hope this helps
Regards
DavidC