M
matthills10
Hi,
I'm (still!) using Project 2000 and have a project file that breaks
down into around 30 distinct 'work packages'.
I need to devolve ownership of these work packages to individual
project managers, so splitting the single project file into a master
and subprojects seems to be the way to go. This will allow the work
packages to be managed as seperate files and will show each project
manager the dependencies they have within the overall project but
external to their own work package.
Each subproject will be relatively small (probably around 100
activities) and there will be a shared resource pool of approximately
80 resources.
My question is: Is this a reasonable way to proceed, or am I likely to
hit problems with this many subprojects and/or resources shared across
them? Any advice or comments from experience most welcome.
Thanks,
Matt
I'm (still!) using Project 2000 and have a project file that breaks
down into around 30 distinct 'work packages'.
I need to devolve ownership of these work packages to individual
project managers, so splitting the single project file into a master
and subprojects seems to be the way to go. This will allow the work
packages to be managed as seperate files and will show each project
manager the dependencies they have within the overall project but
external to their own work package.
Each subproject will be relatively small (probably around 100
activities) and there will be a shared resource pool of approximately
80 resources.
My question is: Is this a reasonable way to proceed, or am I likely to
hit problems with this many subprojects and/or resources shared across
them? Any advice or comments from experience most welcome.
Thanks,
Matt