G
Gregg Richie
System: PS 2007, MSP 2007 Pro, SQL Server 2005, WSS 3.0, Outlook 2003 (Office)
This morning, we made changes to a schedule that pushed a task out 6 months.
After updating, the President still had the original task on his outlook task
list, with the old date.
Here is what I have checked:
- Verified that the project schedule was saved and published
- Checked the queue to ensure nothing was getting hung up
- Verified that the status manager did not have an update approval waiting
(Am I missing something?)
The president is a "bull-in-a-china-shop" kind of operator when it comes to
computers. So he deleted the task and re-imported his assignments from the
server. The assignment did not come back since it is out 6 months.
I know when a previously published task has been deleted from a scheduled
and it is republished, the PWA update sync will remove it from the Outlook
task. So why, in this case, when assigments change to so far in the future,
do they not go delete or update in the Outlook task list when the new task
date is published?
By the way....thanks for the book. It is a life saver.
This morning, we made changes to a schedule that pushed a task out 6 months.
After updating, the President still had the original task on his outlook task
list, with the old date.
Here is what I have checked:
- Verified that the project schedule was saved and published
- Checked the queue to ensure nothing was getting hung up
- Verified that the status manager did not have an update approval waiting
(Am I missing something?)
The president is a "bull-in-a-china-shop" kind of operator when it comes to
computers. So he deleted the task and re-imported his assignments from the
server. The assignment did not come back since it is out 6 months.
I know when a previously published task has been deleted from a scheduled
and it is republished, the PWA update sync will remove it from the Outlook
task. So why, in this case, when assigments change to so far in the future,
do they not go delete or update in the Outlook task list when the new task
date is published?
By the way....thanks for the book. It is a life saver.