Set the start and finish to be in the format of hours:minutes

C

Catfish Hunter

There are 2 places you need to go to. One is under Tools/Option/View. The
date format here sets the format in the "split" at the bottom. To set the
format for the column Date go to View/Tables/More Tables and set the format
her. This only sets this table format. Good Luck!
 
M

Mike Glen

Hi ATOMMC ,

Welcome to this Microsoft Project newsgroup :)

Tools/Options.../View tab. Change the Date format to your requirement by
selecting from the pick list eg: 12:33. That should fix it for all of your
projects.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 