I have created a project plan with standard calendar.
Now I have created a new calendar for our company with saturdays as working
days.
I have changed the calendar for the project by clicking project--project
infm--calendar.
But there are no changes at all in the schedule.
In the Gantt chart also saturday seems to be a holiday.
Why is this happening?
How do I set the newly created calendar as the base calendar for my project?
Meena.
Now I have created a new calendar for our company with saturdays as working
days.
I have changed the calendar for the project by clicking project--project
infm--calendar.
But there are no changes at all in the schedule.
In the Gantt chart also saturday seems to be a holiday.
Why is this happening?
How do I set the newly created calendar as the base calendar for my project?
Meena.