J
j9cleme
Hi and HELP
Just started using Project in a cabinet making shop. The management has
typically used the total price of the project to estimate the duration of the
tasks. For example, if it is a $10,000 project then the blueprints and shop
drawings show take approximately 8 hours.
Does Project have a way of setting the duration time of a task based on the
price of a project?
Any help will be greatly appreiciated.
j9cleme
Just started using Project in a cabinet making shop. The management has
typically used the total price of the project to estimate the duration of the
tasks. For example, if it is a $10,000 project then the blueprints and shop
drawings show take approximately 8 hours.
Does Project have a way of setting the duration time of a task based on the
price of a project?
Any help will be greatly appreiciated.
j9cleme