Redwood said:
Hi everyone,
I need to set Saturday and Sunday as overtime, i want it to automatically
pickup that
a particular resource is working over time and calculate the hours and
costing.
Another Q : Saturdays Overtime is at say $525/h and Sundays is $600 how do i
have both overtime costs?
Thanks in advance
Redwood,
When you say "...set Saturday and Sunday as overtime...", do you mean
that the overtime work is actually scheduled or do you simply mean that
the resource MAY work on weekends and therefore needs to be paid
overtime?
I'll assume that weekend work is NOT scheduled (i.e planned ahead of
time). If there is a single valued overtime rate, it's pretty
straightforward. On the Resource Sheet, enter the overtime rate for each
resource. Then on the Resource or Task Usage views, display Actual
Overtime Work in the timescaled fields on the right. As the work is
performed and you enter a value into the % Work Complete field, Project
will populate the Actual Work field with the scheduled hours. You can
see this on the Resource or Task Usage view. However, for weekend work,
you need to enter a value in the Actual Overtime field on the assignment
rows of the Resource Usage view. Costs will be calculated appropriately.
Having different overtime rates for Saturdays and Sundays presents a
more complex scenario. Although Project does have the ability to
escalate rates over time, doing so for just one day per week will be
neither convenient nor easy. If I had to do it, I would probably use a
VBA macro to distinguish the Sunday actual overtime hours from the
Saturday actual overtime hours and then either dump the total cost into
a spare field or possibly tweak the data in the normal Cost field. Short
of a custom VBA macro, you could use the "analyze timescaled data in
Excel" utility and then apply the appropriate rates to the weekend days
in Excel.
Hope this helps.
John
Project MVP