J
JenIng
I'm looking for a way that I can set a duration of 1 week, but with a work
effort of 2hrs. What I mean by this is, I have one week to complete a task,
but it will only take me 2hrs to actually complete this task. It may be
something I do in one sitting, or it may be something that I work on two or
three times that week.
Does anyone else have this type of project setup and how do you get MS
Project 2003 to comply with this type of setting. Right now all I can do is
say the 1week duration is 40hrs worth or work (but in my case its really only
2hrs, and I just have a week to complete the two hours worth of work b/c I
will have other tasks on other projects happening at the same time).
Any suggestions are appreciated.
effort of 2hrs. What I mean by this is, I have one week to complete a task,
but it will only take me 2hrs to actually complete this task. It may be
something I do in one sitting, or it may be something that I work on two or
three times that week.
Does anyone else have this type of project setup and how do you get MS
Project 2003 to comply with this type of setting. Right now all I can do is
say the 1week duration is 40hrs worth or work (but in my case its really only
2hrs, and I just have a week to complete the two hours worth of work b/c I
will have other tasks on other projects happening at the same time).
Any suggestions are appreciated.