R
Roald
I am trying to setup MS Project 2003 for planning and scheduling, but am
running into problems getting it to do what I want it to.
I have 3 specific questions:
- I need to plan 2 projects for a single resource, with each project having
different working hours (one standard office hours, the other 2 hours a day
in the evening and 4 hours over the weekend). How do I set this up with the
available hours and the amount of work determining the end-date of the
project?
- I have 2 different types of projects/tasks, one operational and one
development. Operational tasks are recurring on specific days of the
week/month and take precedence over development tasks. I have set up both
operational and development tasks, but the assigned resource shows up as
overallocated. I have tried leveling the resource but somehow this does not
work. How do I set up Project so that resource availabiltiy is fixed (i.e. 8
hours a day), operational tasks are prioritised over other tasks and all
other (e.g. dev tasks) are used to fill up the remainder of available hours
on a per-day basis?
- For our operational tasks, some run over several days but only take a few
hours actual/human resource time per day. I have set up a "server" resource
which takes about 90% of the actual hours for the tasks, but need to split
the remaining hours over the duration of the task in a configurable manner.
E.g. for one three day task an operator would have to spend 4/1/3 hours, for
another 2 day task it could be 2/1 hours. Is there a way to set this up?
Thanks in advance.
running into problems getting it to do what I want it to.
I have 3 specific questions:
- I need to plan 2 projects for a single resource, with each project having
different working hours (one standard office hours, the other 2 hours a day
in the evening and 4 hours over the weekend). How do I set this up with the
available hours and the amount of work determining the end-date of the
project?
- I have 2 different types of projects/tasks, one operational and one
development. Operational tasks are recurring on specific days of the
week/month and take precedence over development tasks. I have set up both
operational and development tasks, but the assigned resource shows up as
overallocated. I have tried leveling the resource but somehow this does not
work. How do I set up Project so that resource availabiltiy is fixed (i.e. 8
hours a day), operational tasks are prioritised over other tasks and all
other (e.g. dev tasks) are used to fill up the remainder of available hours
on a per-day basis?
- For our operational tasks, some run over several days but only take a few
hours actual/human resource time per day. I have set up a "server" resource
which takes about 90% of the actual hours for the tasks, but need to split
the remaining hours over the duration of the task in a configurable manner.
E.g. for one three day task an operator would have to spend 4/1/3 hours, for
another 2 day task it could be 2/1 hours. Is there a way to set this up?
Thanks in advance.