Hi,
I have 30 sub-projects inserted in Master project, MSP98. Everythin
working fine except resource sharing. Need expert advice.
The resources are shared in Master and not in different pool file. I
means that my master & pool is the same file.
The problem I face is that all my sub-projects have variations i
standard calendar. In some sub-projects all Saturdays are changed t
working, in some both Saturdays & Sundays are changed to working & i
some few Saturdays are changed to working & in the rest of th
sub-projects Saturdays/ Sundays are not working (standard).
Individual sub-projects when opened, the schedules look as planned a
per the changed calendars, but in Master, the calendar is discarded
standard (Sat / Sundays not working) calendar is applied to al
sub-projects & hence the sub-project finish dates are pushed.
What I am doing wrong ?
Is their a solution , alternate method ?
Help is much apprecaited, Thanks
I have 30 sub-projects inserted in Master project, MSP98. Everythin
working fine except resource sharing. Need expert advice.
The resources are shared in Master and not in different pool file. I
means that my master & pool is the same file.
The problem I face is that all my sub-projects have variations i
standard calendar. In some sub-projects all Saturdays are changed t
working, in some both Saturdays & Sundays are changed to working & i
some few Saturdays are changed to working & in the rest of th
sub-projects Saturdays/ Sundays are not working (standard).
Individual sub-projects when opened, the schedules look as planned a
per the changed calendars, but in Master, the calendar is discarded
standard (Sat / Sundays not working) calendar is applied to al
sub-projects & hence the sub-project finish dates are pushed.
What I am doing wrong ?
Is their a solution , alternate method ?
Help is much apprecaited, Thanks