M
Muddypaws
Hi
I have created a resource pool and have about 9 Plans that I need to
share resources across them all. Now I maybe being dumb here but I
have opened the Resource Pool and then clicked on share resources and
selected the project and the sharer takes precedent, so far ok. Then
I want to open the next plan and link it to my resource pool where the
resource pool takes precedence and so on and so on with the other
plans.
What I am aiming for is that I want to see in the resource pool ALL my
resources available and their useage across all 9 plans, but I can
only seem to see one at a time, is this not possible?
Example I want to see, Finance, Service, Warranty, Rental in my
resource pool as the same people are in all of the above but I can
only seem to see one or the other and not all of them?
Where am I going wrong
I have created a resource pool and have about 9 Plans that I need to
share resources across them all. Now I maybe being dumb here but I
have opened the Resource Pool and then clicked on share resources and
selected the project and the sharer takes precedent, so far ok. Then
I want to open the next plan and link it to my resource pool where the
resource pool takes precedence and so on and so on with the other
plans.
What I am aiming for is that I want to see in the resource pool ALL my
resources available and their useage across all 9 plans, but I can
only seem to see one at a time, is this not possible?
Example I want to see, Finance, Service, Warranty, Rental in my
resource pool as the same people are in all of the above but I can
only seem to see one or the other and not all of them?
Where am I going wrong