B
Barny Blue
I am trying to achieve the shortest possible duration for a task. If I know
already the number of hours it is going to take and who is working on it;
should I enter the task as fixed duration or fixed units?
I have two resources for this task; one has her own part time calendar, the
other works full time. I want to assign them to the task (at 100% units) and
get the shortest possible duration - I know there is a fixed amount of hours
work to be done. When I assign the resources, project gives them half the
work each, so my part time worker is doing 20 of the 40 hours which makes the
duration longer than it needs to be. I am trying to get project to take the
two resources, and bearing in mind their availability, use all their time
until the work is done. So, the full time should be doing more of the work
than the part time.
Any ideas?
Blue.
already the number of hours it is going to take and who is working on it;
should I enter the task as fixed duration or fixed units?
I have two resources for this task; one has her own part time calendar, the
other works full time. I want to assign them to the task (at 100% units) and
get the shortest possible duration - I know there is a fixed amount of hours
work to be done. When I assign the resources, project gives them half the
work each, so my part time worker is doing 20 of the 40 hours which makes the
duration longer than it needs to be. I am trying to get project to take the
two resources, and bearing in mind their availability, use all their time
until the work is done. So, the full time should be doing more of the work
than the part time.
Any ideas?
Blue.