S
Scoobydo133
I am a regular user of planning and scheduling software and only alllow the
use of MS Project for for minor projects or short term schedules.
Can some one explain how I can show the effect of progress on all activity
bars after the status date. I don't want to use the visual Zig Zag lines that
shows me something is late, i want to see the effect of the delay on all
activities after the status date and therfore produce new forecast to
complete dates.
I'm sure there is a simple fix for this as it is a standard plaaning tool.
Thanks
use of MS Project for for minor projects or short term schedules.
Can some one explain how I can show the effect of progress on all activity
bars after the status date. I don't want to use the visual Zig Zag lines that
shows me something is late, i want to see the effect of the delay on all
activities after the status date and therfore produce new forecast to
complete dates.
I'm sure there is a simple fix for this as it is a standard plaaning tool.
Thanks