E
EddieA
I have a series of hundreds of summary groups that have the same number of
tasks and relationships within the group.
What I have is something like this:
The first task is done completly. (Prelimenary revision of a drawings)
The 2nd & 3rds tasks are miles tones set at start to finish with a lag of
5 days. (review & comment cycle for 2 companys).
Task no 4 starts when 2 & 3 are complete with a lag of 3 days.
I would like to be abel to copy & paste intelligently so that the
dependencies work out like the above. The same way Excel does when you cut
and past.
I would also like to have a work amount to be a give % of another. As in
the example above, the work hours for task 4 would need to be 25% of the work
hours for task 1.
I'm new to Project, but I am a pretty decent Excel user so this hinders me
having to repeat all of the data that is so similar in structure (only the
names is different)
Thanks Eddie A.
tasks and relationships within the group.
What I have is something like this:
The first task is done completly. (Prelimenary revision of a drawings)
The 2nd & 3rds tasks are miles tones set at start to finish with a lag of
5 days. (review & comment cycle for 2 companys).
Task no 4 starts when 2 & 3 are complete with a lag of 3 days.
I would like to be abel to copy & paste intelligently so that the
dependencies work out like the above. The same way Excel does when you cut
and past.
I would also like to have a work amount to be a give % of another. As in
the example above, the work hours for task 4 would need to be 25% of the work
hours for task 1.
I'm new to Project, but I am a pretty decent Excel user so this hinders me
having to repeat all of the data that is so similar in structure (only the
names is different)
Thanks Eddie A.