kimg
After I have added new tasks and entered actual work, I insert my constraint
type column and change all constraints to be 'as soon as possible.' I then
update the projects uncompleted tasks to start today. I then level.
What I am seeing are a handful of tasks that are not updating to the new
contraint type. Instead, they are finishing on past dates. When I look at
the tasks Advance tab it has the constraint date of which I want, but the
finish date is not a future date. I noticed that the 0% complete are not
affected in a negative way but the tasks that have some completion of work.
How do I get all my tasks to update with the new SNE?
type column and change all constraints to be 'as soon as possible.' I then
update the projects uncompleted tasks to start today. I then level.
What I am seeing are a handful of tasks that are not updating to the new
contraint type. Instead, they are finishing on past dates. When I look at
the tasks Advance tab it has the constraint date of which I want, but the
finish date is not a future date. I noticed that the 0% complete are not
affected in a negative way but the tasks that have some completion of work.
How do I get all my tasks to update with the new SNE?