SNE constraint

K

kimg

After I have added new tasks and entered actual work, I insert my constraint
type column and change all constraints to be 'as soon as possible.' I then
update the projects uncompleted tasks to start today. I then level.

What I am seeing are a handful of tasks that are not updating to the new
contraint type. Instead, they are finishing on past dates. When I look at
the tasks Advance tab it has the constraint date of which I want, but the
finish date is not a future date. I noticed that the 0% complete are not
affected in a negative way but the tasks that have some completion of work.

How do I get all my tasks to update with the new SNE?
 
R

Reid McTaggart

First, I am confused by your reference to SNE constraints, when you say you
are using the ASAP constraint for all tasks.

Second, perhaps you have set your options to not allow tasks to split. In
that case, tasks with some actual work will not split when you try to
reschedule uncompleted work.
 
J

Jan De Messemaeker

Hi,

The full process should be

Update the tasks
Clear Leveling
Update Project (Reschedule Work)
Level Now

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top