Sorry easy question - how do I calculate total duration in days?

N

ntccfc

Hello, i am running a project with ten different tasks and I would like
to know how I can access the duration of the project in terms of the
amount of days. All I can ascertain at the moment is that the project
starts at 11/04/07 and ends at the 23/07/07 through task information
though how can I simply find out the duration of this in days?

Thanks
 
D

Dale Howard [MVP]

ntccfc --

Click View - Gantt Chart. Click View - Table - Entry. Then click Tools -
Options - View. Select the "Show project summary task" option and then
click the OK button. The Project Summary Task (Row 0 or Task 0) will show
you the Duration of the entire project. I am assuming, however, that you
have entered a Duration for each task and linked the tasks with task
dependencies. You did this, right? Hope this helps.
 