Specify summary levels on which to display rolled up milestones?

D

Dave

All,

I have a Proj2K file with an outline 9 levels deep. Is there a way to
prevent rolled up milestones from displaying on summaries higher than
the next higher level (e.g. display rolled up milestones from an
activity at level 5 on a summary bar at level 4, but not have those ms
roll up to levels 3, 2, and 1 as well)?

Thanks
Dave
 
G

Gérard Ducouret

Hello dave,
For each Summary at higher level, you can clear the "Show Rolled up Gantt
bars" check box in the Summary Task Information / General tab

Hope this help,

Gérard Ducouret
 
D

Dave

Gerard -

Of course! I don't know why I didn't think of that in the first place
- I guess it's just too obvious. My brain must be fading from old age,
just like the rest of my parts! I'm doing all of this programatically,
so I'll have to add a couple of lines of code, but your solution is
just what I need.

Thanks
Dave
 
G

Gérard Ducouret

You're welcome Dave ! :)

Gérard Ducouret

Dave said:
Gerard -

Of course! I don't know why I didn't think of that in the first place
- I guess it's just too obvious. My brain must be fading from old age,
just like the rest of my parts! I'm doing all of this programatically,
so I'll have to add a couple of lines of code, but your solution is
just what I need.

Thanks
Dave

"Gérard Ducouret" <[email protected]> wrote in message
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top