split task without chaging end date

E

ellebelle

Hello,

When there is a split task you can use your cursor to draw time worked
during the split by dragging your cursor along the timeline where the split
occurs.

Is there a tool to do the oppsite of this. If you have a solid task and you
want to quickly mark time not worked without changing the end date or moving
any other splits that may exist later in the timeline?

Thanks,

Ellen
 
R

Rod Gill

Yes. View the Task Usage and for the days you want the Task to show no bar,
enter 0d in the Work row.
 