I am tring to assign two tasks to a predessor that is split. One task will
complete at the end of the split the other at the the beginning of the split.
Can this be done?
 
J

Jan De Messemaeker

Hi,

Sorry, No, links cannot refer to splits, only to tasks as a whole.
If the dates of the split are so important, this should be two tasks anyway.