S
Shawn
Hello,
I'm having difficutly organizing in my project. The problem I have run into
is this.
I have three tasks spread out at different points on my critical path, which
actually are three different phases of one task (eg plumbing underfloor,
topout, and finish). But I recieve one bid that covers all three phases.
Ideally I would like one fixed prorated cost that can be applied all three
tasks. If that makes any sense. Any suggestions? Thank you
I'm having difficutly organizing in my project. The problem I have run into
is this.
I have three tasks spread out at different points on my critical path, which
actually are three different phases of one task (eg plumbing underfloor,
topout, and finish). But I recieve one bid that covers all three phases.
Ideally I would like one fixed prorated cost that can be applied all three
tasks. If that makes any sense. Any suggestions? Thank you