Splited task - false progress

A

Andis

Hi there,
i've splitted a task and added a progress complete which reaches the second
part of the task, but when I add a progress line it still stays at the end of
part 1 of the task despite the actual progress is bigger. In this case the
visual progress line gives a false view.
Thanks in advance
 
B

B Sai Prasad [PMP]

Dear Andis,

I understand your requirement as the progress line stays at the end of first
part of the split task, though the actual progress of the split task is more.

Progress lines are displayed based on the options and details set in
Progress Lines dialog box
1. If you have checked "Always display current progress line", then check if
the project status date or project current date in Project Information is
correct.
2. If you have checked "Display selected progress lines", then check the
date listed under Progress Lines dates list.

Based on the date selected (either in 1 or 2), Microsoft Office Project
identifies the tasks that are on-schedule, and behind schedule.

My guess is the status date or current date in Project Information is before
the second part of the split task.

Please let us know if this helps.

Regards
Sai [PMP]
 
A

Andis

Sai,

Thanks, the info was usefull - I didn't know that Project identifies the
tasks that are on-schedule, and behind schedule.
My progress line was right in the middle of the split. As soon as i set the
progress line date that crossed the second part of the task it straightened
up and the chart looks OK. Changing the project status date didn't bring any
change.

thanks again,
--
Andis Gigulis
Water Ser Ltd.
Project manager


B Sai Prasad said:
Dear Andis,

I understand your requirement as the progress line stays at the end of first
part of the split task, though the actual progress of the split task is more.

Progress lines are displayed based on the options and details set in
Progress Lines dialog box
1. If you have checked "Always display current progress line", then check if
the project status date or project current date in Project Information is
correct.
2. If you have checked "Display selected progress lines", then check the
date listed under Progress Lines dates list.

Based on the date selected (either in 1 or 2), Microsoft Office Project
identifies the tasks that are on-schedule, and behind schedule.

My guess is the status date or current date in Project Information is before
the second part of the split task.

Please let us know if this helps.

Regards
Sai [PMP]


Andis said:
Hi there,
i've splitted a task and added a progress complete which reaches the second
part of the task, but when I add a progress line it still stays at the end of
part 1 of the task despite the actual progress is bigger. In this case the
visual progress line gives a false view.
Thanks in advance
 
B

B Sai Prasad [PMP]

Dear Andis,

Thanks for your feedback.

As per your statement ".. Changing the project status date didn't bring any
change." is because "Status Date", by default, is NA and needs to set in the
Project Information form (Project > Project Information ...)

Please let us know if this helps.

Regards
Sai [PMP]


Andis said:
Sai,

Thanks, the info was usefull - I didn't know that Project identifies the
tasks that are on-schedule, and behind schedule.
My progress line was right in the middle of the split. As soon as i set the
progress line date that crossed the second part of the task it straightened
up and the chart looks OK. Changing the project status date didn't bring any
change.

thanks again,
--
Andis Gigulis
Water Ser Ltd.
Project manager


B Sai Prasad said:
Dear Andis,

I understand your requirement as the progress line stays at the end of first
part of the split task, though the actual progress of the split task is more.

Progress lines are displayed based on the options and details set in
Progress Lines dialog box
1. If you have checked "Always display current progress line", then check if
the project status date or project current date in Project Information is
correct.
2. If you have checked "Display selected progress lines", then check the
date listed under Progress Lines dates list.

Based on the date selected (either in 1 or 2), Microsoft Office Project
identifies the tasks that are on-schedule, and behind schedule.

My guess is the status date or current date in Project Information is before
the second part of the split task.

Please let us know if this helps.

Regards
Sai [PMP]


Andis said:
Hi there,
i've splitted a task and added a progress complete which reaches the second
part of the task, but when I add a progress line it still stays at the end of
part 1 of the task despite the actual progress is bigger. In this case the
visual progress line gives a false view.
Thanks in advance
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top