J
Jason
Hello everyone,
I have a pipe detail that the shop can work on it until so long until they
need the equipment to do their final work. So, the piping can be complete to
a certain percentage then it comes to a halt until the arrival of the
equipment.
Anyways, what can I do to tell project that I want certain percentage of the
task to split and that split to be placed lets say equipment arrival
ff+2days.
thank you
I have a pipe detail that the shop can work on it until so long until they
need the equipment to do their final work. So, the piping can be complete to
a certain percentage then it comes to a halt until the arrival of the
equipment.
Anyways, what can I do to tell project that I want certain percentage of the
task to split and that split to be placed lets say equipment arrival
ff+2days.
thank you