Spread effort across project

M

MbX

Is it possible to define a task, each day (or week) until the last day of the
project taking up the same amount of time (e.g. each day taking 2 hours of
work)?
 
G

Gérard Ducouret

MbX,
Have you tried the Insert / Recurring Task feature ?
Hope this helps,

Gérard Ducouret
 
M

MbX

That was indeed what I was looking for! Thank you Gérard!

In the ideal world however, I would not have to specify an end day, but
rather the end of the project: when the project ends, the recurring task ends!
 
G

Gérard Ducouret

MbX,

You are welcome!

Gérard Ducouret

MbX said:
That was indeed what I was looking for! Thank you Gérard!

In the ideal world however, I would not have to specify an end day, but
rather the end of the project: when the project ends, the recurring task
ends!
 