xlsstudent
hi,
I am managing a complex program and need help in resource allocation.
My Business analyst works on BA activities let us say for 3 days and hands
over to my tech architect. My tech architect may need about 10 days while my
BA starts working on next package. There has to be a meeting between the
architect, BA and clients once my arhcitect is ready. my challenge is, how do
I allocate the BA in split form? If I say my BA will work on package1 from
day1 to day 3 and on package 2 from day 4 to day20. If the meeting with
client happens on day 18, then my BA will be 200% loaded which is
impractical. So need help to address this.
Also, is there a way, where project assigns resources only for 8hrs, and if
the resource already has 8hrs of work with higher priority will automatically
assign the work to next day?
I am managing a complex program and need help in resource allocation.
My Business analyst works on BA activities let us say for 3 days and hands
over to my tech architect. My tech architect may need about 10 days while my
BA starts working on next package. There has to be a meeting between the
architect, BA and clients once my arhcitect is ready. my challenge is, how do
I allocate the BA in split form? If I say my BA will work on package1 from
day1 to day 3 and on package 2 from day 4 to day20. If the meeting with
client happens on day 18, then my BA will be 200% loaded which is
impractical. So need help to address this.
Also, is there a way, where project assigns resources only for 8hrs, and if
the resource already has 8hrs of work with higher priority will automatically
assign the work to next day?