T
TraceyH
Hello,
From Tools/Change working time I changed the standard calendar to work
4hrs/day, 20hr/wk, 20days/month immediately after creating a new project file
Then I entered Task Name info. Next I entered estimated Work for each task.
Then I assigned a resource.
Next I leveled the entire project. In the Resource View I am noticing my
resource is showing availability at 8hrs/day...and the leveling is still
allocating him as working 8hrs/day.
What have I done wrong? I want all my resources on a project to be at 50%
utilization
From Tools/Change working time I changed the standard calendar to work
4hrs/day, 20hr/wk, 20days/month immediately after creating a new project file
Then I entered Task Name info. Next I entered estimated Work for each task.
Then I assigned a resource.
Next I leveled the entire project. In the Resource View I am noticing my
resource is showing availability at 8hrs/day...and the leveling is still
allocating him as working 8hrs/day.
What have I done wrong? I want all my resources on a project to be at 50%
utilization