Start and Finish Times

T

Tan777

When working in project as I enter my information the start and fininsh times
keep switching back and forth to other times. I have to keep re-entering the
times several times before it will accept the information.
 
J

JulieS

Hi Tan777,

Welcome to the project newsgroup.

I can see why you are having difficulty. You should not be entering
dates/times into a project file. Although a project file looks a great
deal like a spreadsheet (Excel file) the start and finish dates are
meant to be calculated by the program.

I suggest you take a look at fellow MVP Mike Glen's series of articles
on MS Project to get you started in the right direction. A link to his
articles can be found at:

http://project.mvps.org/mike's_tutorials.htm

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 
J

Jan De Messemaeker

Hi,

It's a miracle it accepts them after several trials because it isn't made to
accept YOUR dates, it is meant to calculate dates based on your input
(duration, links to other taks, constraints..)
HTH
 