I would like to program activities along the day.
How could I set in the field Start, at what TIME the activities must been
done ? (It only accept days) Thanks.
 
J

Jan De Messemaeker

Hi,

Behind the date write a blank and then the time of day:

23/6/6 8:44

To see the time of day everywhere, Tools, Options, View, in date format
select the format that has time of day (the one at the top of the list)

HTH
 