How can I display the Current Date and/or the Status Date (as a vertical
line) in the Resource Usage view ?
Using Project Pro 2003.

Thanks
 
D

Dale Howard [MVP]

Newbie --

If you apply the Resource Usage view and then click Format - Gridlines, you
will see that the Current Date and Status Date are not available gridlines
in this view. Sorry.

On the other hand, if you apply the Gantt Chart view and click Format -
Gridlines, you will see that both Current Date and Status Date can be added
and formatted in this view. Hope this helps.
 
N

Newbie

Hello Dale,
Thanks for the information !

Newbie

Dale Howard said:
Newbie --

If you apply the Resource Usage view and then click Format - Gridlines, you
will see that the Current Date and Status Date are not available gridlines
in this view. Sorry.

On the other hand, if you apply the Gantt Chart view and click Format -
Gridlines, you will see that both Current Date and Status Date can be added
and formatted in this view. Hope this helps.
 