Hi,

I have set up a baseline and then selected the "Check the progress of the
project" link. I have filtered the form to "All Tasks" ,and the status date
to today.

However, no indicators are displaying in the the Status Indicator field.

Steve
 
S

sosvideo

Problem Solved .....

Although the start date of the project has passed, the start date of the
first task hasn't. Obviously, Project won't assign a status indicator until
the current date is within the start/finish time of a task.