Hello,
Two weeks ago, I discovered a strange feature in Project Pro 2007 : a
resource was assigned at 25% on a complete task. I added some remaining
duration on this task and Project sent a message :
"You can continue at 25% or at 100% for that resource. What is your choice?"
I tried the same feature on another PC with Project 2003 and it worked the
same way.
Today, I tried again on the two PCs without any success: this strange
feature is gone.
Have you meet this feature? In which conditions ?
Thanks for your help
Robert
Two weeks ago, I discovered a strange feature in Project Pro 2007 : a
resource was assigned at 25% on a complete task. I added some remaining
duration on this task and Project sent a message :
"You can continue at 25% or at 100% for that resource. What is your choice?"
I tried the same feature on another PC with Project 2003 and it worked the
same way.
Today, I tried again on the two PCs without any success: this strange
feature is gone.
Have you meet this feature? In which conditions ?
Thanks for your help
Robert