Sub - Contractors

S

Scott Strenger

How would I enter Sub Contractors, and there cost per Project? And will it
show up in the report?
 
D

davegb

Scott said:
How would I enter Sub Contractors, and there cost per Project? And will it
show up in the report?

The people they supply you would be resources. If you want to track
which resources, you could group them as Subs, or under the name of
their company. You could also use Resource Notes or custom fields to
track them. They'd show up in Resource reports.
 