M
Martin Wilkinson
I have a master project with 4 sub projects (Proj 2000).
The sub projects have summary tasks.
When open a sub project stand alone, I can update a task's % Complete value
and the Summary Task's % Complete is updated/calculated.
When I open the sub project from within the Master project, and update the
same task's % Complete value, the Summary task's value stays at zero. It
seems that nothing I do will make the Summary task's values budge from 0.
I have auto calculation on.
Anyone seen this behaviour with sub-projects before?
Cheers
martin
The sub projects have summary tasks.
When open a sub project stand alone, I can update a task's % Complete value
and the Summary Task's % Complete is updated/calculated.
When I open the sub project from within the Master project, and update the
same task's % Complete value, the Summary task's value stays at zero. It
seems that nothing I do will make the Summary task's values budge from 0.
I have auto calculation on.
Anyone seen this behaviour with sub-projects before?
Cheers
martin