I have ten subtasks, each are one month apart, my duration shows 196 days but
i am only bussy 10 days how do i fix the duration?
 
G

Gérard Ducouret

Schalk,

The duration of the Summary task (Calculted by Project, not entered by you)
is not the sum of the subtasks durations. It spans from the begining of the
earliest subtask to the end of the last one.

Gérard Ducouret
 
S

Schalk

Thank you, is their no way to diplay the days that i work and not the total
duration.
 