Successor task (T2) start day same as predeccessor task (T1)

W

wjBigSax

How can I get a successor task (T2) start to be same day as predeccessor task
(T1) completion? [I saw other posts asking how do do the opposite, which I
don't want but am getting.]

(I posted a similar but didn't see posted anywhere.)
 
J

Jan De Messemaeker

Hi,

That will be the case unless an other predecessor pushes it further... but
if that is the case, why not show?
 
G

Gérard Ducouret

Hi,

If the predecessor is on row 10 : the link will be 10SS (Start-Start)

Gérard
 
G

Gilgamesh

Gérard Ducouret said:
Hi,

If the predecessor is on row 10 : the link will be 10SS (Start-Start)

Actually they will need 10FS-1day
Ypurswillwork only if 10 is a 1 day task.
Gérard


wjBigSax said:
How can I get a successor task (T2) start to be same day as predeccessor task
(T1) completion? [I saw other posts asking how do do the opposite, which I
don't want but am getting.]

(I posted a similar but didn't see posted anywhere.)
 