Task that start and ends at same date that another task

C

Carles

I have two task (T1 & T2). How can I indicate than T1 have to start and
finish at the same date that T1?

Thank you.
 
J

Jan De Messemaeker

Hi Carles,

There may be (rather dangerous) ways to do that through OLE links, but with
normal Project functions, no, sorry, no go.
 
J

Jim Aksel

Two tasks that must run entirely parallel. In effect you want SS and FF
constraints on both T1 and T2. That's a no go.

Here is a work around. I assume T0 is a predecessor to T1, so link it that
way FS. This establishes the start of T1.
Insert a milestone T1a as FS from T1 and 0 day duration. T1a now finishes
on the same day that T1 finishes.

Make T2 a Hammock Task. The start of T2 is linked to the start of T1, the
finish of T2 is linked to the finish of T1a. Creating a Hammock Task is
covered in the FAQ#19 at http://project.mvps.org/faqs.htm

T2 will now march with T1. Does that help?

If this helps, please consider rating the response.
 