Task Start Date

J

Jerry Mc Cauley

Good afternoon,

Anyone have an idea on this?

I have a task (T2) that follows another (T1). T2 must start on tge Friday
following T1's finish. The T2 task will run until the following Thursday and
conclude.

(This equals ---- a set-up function finishes and a sample billing cycle must
be done)

Any ideas?

Thanks in advance.
 
J

Jack Dahlgren

Insert a task T2p which goes between the two of them.
Create a calendar for T2p which only has working time after say 5 PM on
Thurs and before 8:00 Am on Fri.
Set the duration of task T2p to some very small amount (less than the
available working time.

Then T1 will complete and the successor T2p can not start until after
Thursday and before Friday morning, then T2 will start on Friday.

-Jack Dahlgren
 
J

Jerry Mc Cauley

Jack,

Wow - how simple. Thanks Jerry
--
Jerry


Jack Dahlgren said:
Insert a task T2p which goes between the two of them.
Create a calendar for T2p which only has working time after say 5 PM on
Thurs and before 8:00 Am on Fri.
Set the duration of task T2p to some very small amount (less than the
available working time.

Then T1 will complete and the successor T2p can not start until after
Thursday and before Friday morning, then T2 will start on Friday.

-Jack Dahlgren
 