summary of the resource capacity

J

JustMe

I have a project schedule with multiple resource with % of productivity
and vacation block out, and I would like to find out the capacity of
each resource from now till the end of the project. Any pointer how to
do it from Project schedule? Thanks.

Frank
 
J

JulieS

Hi Frank,

Try the Resource Usage view and add "Remaining Availability" to the
timescaled portion (right side of the view). This will show the number
of available hours based upon the Resource's calendar, max. units, and
work already assigned.
--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 