C
Christy
I have a project with tasks outlined as summary tasks and
subtasks, and I have saved the baseline. On the summary
tasks, the fields "Actual Start", "Actual Finish", and "%
complete" are NA, NA, and 0%, and they are greyed out so
that they cannot be updated. I need for these fields to
be updated and get their information from the subtasks.
Is there a way to do this?
Thanks,
Christy
subtasks, and I have saved the baseline. On the summary
tasks, the fields "Actual Start", "Actual Finish", and "%
complete" are NA, NA, and 0%, and they are greyed out so
that they cannot be updated. I need for these fields to
be updated and get their information from the subtasks.
Is there a way to do this?
Thanks,
Christy