Hello!
I have a summary task
that has
Task A 10 hrs
Task B 20 hrs
Task C 30 hrs
Task D 40 hrs
now my summary task says the total duration is 10 hours
if i link task b and task c then my summary duration is 60 hours
but i really want the whole 100 hours in the summary duration.
how do i get all the 100 hours with out having task D have a predesscessor?
thanks