Viadelprado
I just loaded project and started simple task and neither summary task or
linking works
I put in summary on line1
t1 on line two - duration 3 days
t3 on line 4 duration 2 days
I then indent lines 2 and 3 and line 1 summary only shows 1 day duration
I also link lines 2 to 3 and the start date on line 3 does not change
Is there a setup that I'm missing