A
andyb
Hi, I'm new to MS Project 2002. I'm used to SureTrak that had a handy
"Expected Finish" check box. In it, I could tell the program to assume that
the task would end on a particular day and would automatically deduct the
right amount of days from the Remaining Duration. I know there is an "Update
work through" box, but I only want this done for a few items (if I say for
selected tasks, then I can't come back with updating everything else). How
can I do this?
"Expected Finish" check box. In it, I could tell the program to assume that
the task would end on a particular day and would automatically deduct the
right amount of days from the Remaining Duration. I know there is an "Update
work through" box, but I only want this done for a few items (if I say for
selected tasks, then I can't come back with updating everything else). How
can I do this?