Hello, would you please help me with this problem?........i would like to
know what is the best and fastest way to resolve this scenario without
afecting the project plan....
I have a master with all the projects that the department handles and there
is a repetitve task call MRD that is the predecesor of all other tasks..we
have diferent ppl working at the same time reviewing this document and it is
posted as let's say 1 week for completion....so that means that i have
overlocated at least 10 ppl because they are reviewing 10 different MRDs the
same week....what's the best way to resolve this?
Thansk for the help!!
know what is the best and fastest way to resolve this scenario without
afecting the project plan....
I have a master with all the projects that the department handles and there
is a repetitve task call MRD that is the predecesor of all other tasks..we
have diferent ppl working at the same time reviewing this document and it is
posted as let's say 1 week for completion....so that means that i have
overlocated at least 10 ppl because they are reviewing 10 different MRDs the
same week....what's the best way to resolve this?
Thansk for the help!!