Task bar ?

S

s conklin

How do you change task bar for internal task to external task, Very new to MS
Project and got thrown into this at the last minute...any help would be
appreciated.
 
D

Dale Howard [MVP]

s conklin --

I'm not really sure WHY you would want to do this, but if you really need to
know, here's how:

1. Apply the Gantt Chart view.
2. Double-click anywhere in the white part of the Gantt Chart.
3. In the Bar Styles dialog, select the Task item at the top of the list.
4. At the bottom of the dialog, change the Color pick list item to Gray.
5. Click the OK button.

Hope this helps.
 