mmilos
I am currently working a large plan for multiple sites. The Base calendar is
the normal 8 to 5 M-F with weekends off. I have one task the long pole which
is 120 days lead time but the days are consectutive. The 120 day task has
constraints within the normal plan. I'm having trouble getting the 120 day
task to be 120 days because of the constraints to the normal calendar. How
do I fix this??
Thanks
the normal 8 to 5 M-F with weekends off. I have one task the long pole which
is 120 days lead time but the days are consectutive. The 120 day task has
constraints within the normal plan. I'm having trouble getting the 120 day
task to be 120 days because of the constraints to the normal calendar. How
do I fix this??
Thanks