I am currently working a large plan for multiple sites. The Base calendar is
the normal 8 to 5 M-F with weekends off. I have one task the long pole which
is 120 days lead time but the days are consectutive. The 120 day task has
constraints within the normal plan. I'm having trouble getting the 120 day
task to be 120 days because of the constraints to the normal calendar. How
do I fix this??

Thanks
 
J

Jonathan Sofer

Mike

Have you tried creating and then applying a "working weekend" type calendar
to the 120 day task? This is done under "Advanced Tab" of the task
information screen? If you have resources assigned to this task also check
the box to "ignore resource calendars".

Jonathan
 
M

Mike Glen

Hi mmilos,

Welcome to this Microsoft Project newsgroup :)

Have you tried a lead of 120ed for elapsed days?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top