KT said:
Hi John, Dale and Pratta
Thanks!! I really appreciate your suggestions. I am actually learning this
Microsoft Project gradually by feeding in some project information and
experimenting it. The process that we follow in our projects is dependent on
several factors and so the tasks. Hence we don't know the start and finish
time for some tasks until the project is like 20 percent complete. Let me
explain a little bit in detail. Say the development process of the project
has five phases. We won't know the start and finish dates for the Phases Two
through Five until we complete Phase One. So our agreement with the client
would be that the project completion time will differ according to the
completion of each phase. With this background, and reading about the
baselines, I understood that before saving a baseline I should have the
initial schedule of the whole project. In this case I don't have one upfront.
So I am concerned of the steps I should follow to achieve setting up the
baselines and tracking the progress of the project. Can somebody please help
me with this? Thanks in advance.
Also I have another question which is not related to the baseline. When I
enter a task in the Gantt chart view, Project automatically estimates the
task duration as one day. But, the start date and end date are different in
this case. If the duration is one day, then the start and finish date should
be the same. Anybody know why this happens? Thanks
KT
KT,
Hopefully the other guys will check in with their suggestions also but
here is my two cents.
The fact that you can't nail down the start and finish for future phases
is nothing unusual. In fact, it is the norm. If we could nail down
anything in the future we would be sought after by people far and wide.
So, what do you do? Estimate as best you can based on a number of
factors. Use historical data for one. Compare this project to previous
similar projects to gage task durations. If you don't have historical
data, talk to the people who will be doing the work. They probably have
the best feel for how long tasks their tasks will take. However,
sometimes you just have to use an educated guess. The bottom line is
that you have to have a starting plan. Will it be wrong? Definitely.
Nobody, even the best Project Managers, get it right on the first cut.
The world is dynamic. Things are gonna change no matter how well you
plan. No matter, set the initial baseline. When you get a better handle
on future tasks, set another baseline (the latest version of Project has
provisions for multiple baselines) or just re-baseline the future tasks
with mutual agreement with the customer. Everything should be negotiated
- budget, baseline, performance measures, etc. That's just good
management and good customer relations.
With regard to estimated durations. Seeing a different date for the
start and finish of a one day task can be caused by a couple of things.
First, go to Tools/Options/Calendar tab. Look at the setting for "Hours
per day". The default is 8 hours but if it has been increased, say to 9
hours per day, the finish of a one day duration task will be on the next
day. If the "Hours per day" is at the default, go to Tools/Change
Working TIme. For any workday, the default "From" and "To" should be
8:00 am to 12:00 pm and 1:00 pm to 5:00 pm. If the working hours has
been changed such that the total hours in a day is less than 8 (based on
the default setting in Tools/Options), the finish date of a one day
duration task will be on the next day.
Wow, a lot of stuff to try and get a handle on huh? But, that's why we
are here. Hope this helps.
John
Project MVP