Task Duration in Seconds?

P

Paul

We are a manufacturer of high-speed assembly machinery. A
key task in the design of a system is compiling a cycle
time chart for the machine. Essentially this is a Project
chart - however the task durations are in seconds or
fractions of a second. Is there a way to use Project to
accomplish this?

Thanks.
 
J

John

Paul,
Project's smallest time increment is the minute and all its calculations
are done in minutes, whole minutes, no fractions. The best you can do is
to equate a Project minute to seconds, however beyond hours (minutes in
your case), the time relationship will need to be modified since
obviously there aren't 60 hours in a day.

Hope this helps.
John
 
G

Gérard Ducouret

Hello Paul,

As some others of my clients who do the same thing, you can assume that "a
minute for Project is a second for me"...

Hope this helps,

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris
 
P

Paul

Thanks for the ideas! I am currently doing the minutes-to-
seconds conversion. Thought someone might have other
ideas. Also have a rather clumsy Excel program that does
work in seconds. However it is no where near as flexible
as Project.
-----Original Message-----
Hello Paul,

As some others of my clients who do the same thing, you can assume that "a
minute for Project is a second for me"...

Hope this helps,

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris

"Paul" <[email protected]> a écrit dans le message de
We are a manufacturer of high-speed assembly machinery. A
key task in the design of a system is compiling a cycle
time chart for the machine. Essentially this is a Project
chart - however the task durations are in seconds or
fractions of a second. Is there a way to use Project to
accomplish this?

Thanks.


.
 