S
Stephen Moras
Hi guys,
I have a strange problem. I have a task which say takes 80 days to finish.
When i put 2 resources it takes 40 days and the more resources i put in the
more the duration reduces which makes sense. But when i am say entering maybe
the 7th or 8th resource the duration instead of reducing actaully increases.
This weird problem is not consistent and i cannot replicate at will..For a
mkoment i thought maybe its becoz the resource i have put in is on leave, so
ic hecked their calendars but no problem there..So i am bit puzzled..
In whch conditions does a task duration increase when more resources r put
in. IS there a limit to the number of resources for a task?
I have a strange problem. I have a task which say takes 80 days to finish.
When i put 2 resources it takes 40 days and the more resources i put in the
more the duration reduces which makes sense. But when i am say entering maybe
the 7th or 8th resource the duration instead of reducing actaully increases.
This weird problem is not consistent and i cannot replicate at will..For a
mkoment i thought maybe its becoz the resource i have put in is on leave, so
ic hecked their calendars but no problem there..So i am bit puzzled..
In whch conditions does a task duration increase when more resources r put
in. IS there a limit to the number of resources for a task?