A
almacote
I searched the forum for this answer but couldn't find help. I hope I'm not
duplicating any posts.
I continue to have intermittant difficulties with the above issue. There
are times when I add tasks (Example: 16 hrs duration), and then add 2
mechanics with 100% availability with the task. SOMETIMES the task duration
nets to 8 hrs and SOMETIMES it stays at 16 hrs. I've tried to open NEW MS
Project files to test this and it acts differently many times. There are no
global settings set up. In my working file I've tried to un-link, un-indent
and reset the entire file to As-Soon-As-Possible constraints JUST in case I
inadvertantly forced something.
I hope someone can tell me why this is happening so I can work with it. My
HOPE is that adding 2 men to a total task duration will decrease that
duration.
Thanks in advance!
duplicating any posts.
I continue to have intermittant difficulties with the above issue. There
are times when I add tasks (Example: 16 hrs duration), and then add 2
mechanics with 100% availability with the task. SOMETIMES the task duration
nets to 8 hrs and SOMETIMES it stays at 16 hrs. I've tried to open NEW MS
Project files to test this and it acts differently many times. There are no
global settings set up. In my working file I've tried to un-link, un-indent
and reset the entire file to As-Soon-As-Possible constraints JUST in case I
inadvertantly forced something.
I hope someone can tell me why this is happening so I can work with it. My
HOPE is that adding 2 men to a total task duration will decrease that
duration.
Thanks in advance!